Break rate cut from 14 to 5 per month
Break prediction with a 92-second median lead time gave the crew time to trim a nip or a draw instead of threading. 33 equivalent production hours recovered per month.
Every figure on this page is reconciled against the mill's own historian and reel records over a defined baseline period, not against our telemetry. All engagements are design-partner pilots [ASPIRATIONAL — pre-launch].
Live example: Grade change PM4 · 135 gsm kraftliner → 110 gsm testliner, no break, ≤14 min off-spec
Different grades, different wedges, same measurement discipline.
Break prediction with a 92-second median lead time gave the crew time to trim a nip or a draw instead of threading. 33 equivalent production hours recovered per month.
Twin-rehearsed transition sequencing across 11 changes a week took off-spec tonnage from 9.8 t to 6.2 t per change and transition time from 19:05 to 11:42.
Full CD actuator control tightened basis-weight 2σ from 2.6 to 1.7 g/m² and reduced quarterly customer claims from seven to two.
Yankee and hood rebalancing against live moisture removed the over-dry margin while tightening moisture 2σ from 0.31 to 0.19.
The exact run the 22% figure is built on — 135 gsm kraftliner to 110 gsm testliner, executed under bounded autonomy with one human approval gate.
Mill Orchestrator — Pulled the 110 gsm testliner spec, customer tolerances and the standing energy budget from mill MES; locked the target envelope for the run.
Mill Orchestrator — Simulated 48 candidate transition recipes on the as-run paper-machine twin — forming, press, dryer and calender — and ranked them on off-spec tonnes, break risk and steam.
Pulp-and-Stock — Stepped refiner specific edge load 1.9 → 1.4 Ws/m and pushed freeness toward 412 CSF while consistency held at 3.4%.
Wetend-and-Chemistry — Retention aid trimmed to 214 g/t and sizing to 1.1 kg/t against live charge and turbidity; first-pass retention recovered to 78% inside 90 seconds.
Form-and-Press — Re-cut the slice profile across 78 actuators and set jet-to-wire to 0.994 to hold formation index through the basis-weight ramp.
Form-and-Press — Nip load reduced 620 → 540 kN/m to protect the lighter web; post-press dryness landed at 47.1%.
Dry-and-Coat — Re-phased the steam schedule across 6 dryer groups and rebalanced the hood; reel moisture converged to 7.4% ±0.19 2σ at 6.1% less steam than the standing recipe.
Defect-and-Inspect — 18 line-scan cameras streaming; two edge-crack precursors detected at the drive side and cleared by a 40 kN/m nip trim before either propagated.
Mill Orchestrator — Speed ramp 1,180 → 1,245 m/min exceeded the site autonomy threshold. Held for the machine tender; approved by J. Okonkwo at 04:57:12.
Quality-and-Conformance — Reel R-24188 released: full genealogy written (furnish, chemistry, CD profiles, defect map, operator actions) and checked against grade spec.
Nothing in the case study is a claim you cannot trace back to a timestamped call.
Plan → thought → action → observation, exactly as the orchestrator recorded it.
Move PM4 from 135 gsm kraftliner to 110 gsm testliner with zero breaks and under 14 minutes of off-spec production.
Simulate the transition on the twin first. Lead with stock and chemistry so the furnish is right before the basis weight ramps, then trim forming and press, then re-phase drying. Watch the web continuously; hold the speed ramp for a human.
The standing recipe drops basis weight and speed together. On the twin that produces a 3-minute moisture excursion because the dryer section unloads faster than the steam schedule can follow. Sequencing the steam re-phase ahead of the basis-weight ramp removes it.
twin.simulate(candidates=48) → recipe #31 re-phases steam 40 s before the basis-weight ramp and holds nip load until post-press dryness confirms.
Recipe #31 estimates 6.4 t off-spec against 9.8 t for the standing recipe, with break risk 0.07. Two candidates scored lower on steam but raised break risk above the 0.15 site limit and were discarded.
Execute recipe #31 under autonomy level L3: nine setpoint writes permitted, speed ramp routed to the machine tender.
Edge-crack precursor at 1,412 mm drive side at 04:56:41. Nip trim of −40 kN/m in press-2 cleared it in 16 s without a break.
Run complete in 11 m 42 s. 6.2 t off-spec, zero breaks, 6.1% less dryer steam than the standing recipe. Reel R-24188 released with full genealogy.
Baseline period is 13 weeks immediately preceding deployment; measurement period is 13 weeks after the supervised-write phase began.
| Mill · machine | Metric | Baseline | With Pulpum | Change |
|---|---|---|---|---|
| Nordkraft PM4 | Breaks / month | 14 | 5 | −64% |
| Nordkraft PM4 | Threading hours / month | 19.6 | 7.0 | −64% |
| Aurora BM2 | Off-spec t / change | 9.8 | 6.2 | −37% |
| Aurora BM2 | Transition time | 19:05 | 11:42 | −39% |
| Ternvik PM1 | CD basis 2σ (g/m²) | 2.6 | 1.7 | −35% |
| Ternvik PM1 | First-pass quality | 91.4% | 96.8% | +5.4 pts |
| Cascadia TM3 | Steam / tonne (GJ) | 2.41 | 2.22 | −7.9% |
| Cascadia TM3 | Moisture 2σ | 0.31 | 0.19 | −39% |
| Valle PM2 | Freeness deviation (CSF) | ±11 | ±4 | −64% |
| Hokuriku PM5 | Release records complete | 86% | 99.2% | +13.2 pts |
What actually changed on the machine, not just what changed on the report.
The mill had a break rate it could not explain and a break log with no precursor characterisation. Eleven weeks of labelled break replays trained an edge model that surfaces edge-crack, flutter and wrinkle precursors with usable lead time.
| Signal | Before | With Pulpum |
|---|---|---|
| Breaks / month | 14 | 5 |
| Median lead time | 0 s | 92 s |
| Broke t / month | 410 | 160 |
The site had a hard energy target and had already taken the easy reductions. The remaining margin was in over-drying, protected by moisture variation nobody wanted to touch on a tissue machine.
| Signal | Before | With Pulpum |
|---|---|---|
| Steam / tonne | 2.41 GJ | 2.22 GJ |
| Moisture 2σ | 0.31 | 0.19 |
| Crepe deviation | baseline | unchanged |
A case study is only useful if the method survives scrutiny from the mill's own process engineers.
Thirteen weeks immediately preceding deployment, extracted from the mill's systems, agreed in writing before anything is installed.
Results are normalised for grade mix and machine speed. A quarter with an easier order book does not become a Pulpum result.
Planned shutdowns, known equipment failures unrelated to control, and commissioning weeks are excluded from both periods.
Where a mechanical upgrade or a furnish change coincided with deployment, it is named in the study and the figure is qualified.
Every published figure is signed off by the site's process engineering lead before it appears here.
The underlying run records are available to the customer in full, and to prospects under NDA.
Across all design-partner engagements [ASPIRATIONAL].
Figures are design targets and pilot-scoped results [ASPIRATIONAL]. Every number is reproduced from the mill's own reel genealogy, not our telemetry.
Autonomy earns trust one shift at a time. These are design-partner quotes from pilot deployments [ASPIRATIONAL].
"The first thing that convinced the crew wasn't the control — it was the log. You can scroll back and see exactly why it dropped the nip. Nobody argues with a timestamp."
Machine tender · PM4 · Nordkraft Mills
"We had two people who could do a clean 135-to-110 transition. One retired in March. The twin now does the sequencing and the second one supervises it."
Production manager · Aurora Board
"Break prediction was the wedge. Ninety seconds of warning is the difference between a nip trim and four hours of threading."
Process engineer · Ternvik Paper
A mill does not go from manual to unattended in one step. Pulpum makes the level explicit, auditable and reversible at any time.
| Level | What the agent does | What the human does | Typical time to reach |
|---|---|---|---|
| L1 · Advisory | Recommends setpoints and explains why | Enters every change manually | Week 1 |
| L2 · Supervised | Proposes a write; it executes on approval | Approves each write in the HMI | Week 3–6 |
| L3 · Bounded | Writes inside tag, rate and magnitude limits | Approves ramps and grade releases | Month 2–4 |
| L4 · Unattended | Runs the envelope without prompting | Sets the envelope; reviews the shift record | Month 6+ [ASPIRATIONAL] |
Pulpum writes to production equipment. Every capability is scoped, every write is policy-checked, and every action is written to an append-only audit log the mill owns.
| Standard | Scope | Status |
|---|---|---|
| SOC 2 Type II | Cloud control plane | RUNNING In progress [ASPIRATIONAL] |
| ISO 27001 | Company-wide ISMS | QUEUED Planned [ASPIRATIONAL] |
| IEC 62443 | Mill-edge OT security | RUNNING Design-aligned |
| GDPR | Operator data | SUCCEEDED Compliant |
| ISO 9001 / FSC | Quality + chain of custody records | SUCCEEDED Supported |
The questions mill managers and process engineers actually ask in the first meeting.
Yes, but only within an explicit tag allow-list with per-tag rate and magnitude limits, and only at the autonomy level your site has set. Level 1 is advisory-only: Pulpum recommends and a human enters everything. Most mills spend their first weeks there before enabling supervised writes.
Control returns to the DCS last known-good state within one scan cycle. Pulpum is designed as a supervisory layer on top of your existing control system, never as a replacement for it, so a Pulpum outage degrades the mill to its current way of running — not to a stop.
Break prediction and defect classification typically need 8 to 12 weeks of QCS, DCS and inspection history per grade family, plus labelled break events. Advisory recommendations start in week one from the physics-based twin, and improve as mill-specific history accumulates.
Only if you choose cloud training. Recipes, grade models and defect libraries are tenant-isolated and never used to train another customer's models. A fully on-prem deployment with an air-gapped mill edge is available for sensitive producers.
You are, the same as with any control strategy — which is why every write is policy-checked, bounded, logged and reversible, and why anything above your risk threshold waits for a named approver. The audit log records the request, the reasoning, the limits applied and the human decision.
A 90 to 120 day mill-edge deployment on one paper machine, scoped to a single workflow with a pre-agreed baseline [ASPIRATIONAL]. Weeks 1–3 are connection and shadow-mode observation; weeks 4–8 advisory; weeks 9+ supervised or bounded writes if the mill is satisfied with the recommendations.
A mill review starts with your historian extract and ends with a wedge, a baseline and a payback estimate in your own numbers.
↑↓ navigate↵ openesc close